Tuesday, April 5, 2011

TOYOTA CITY'S SUPPLIERS, FAR FROM QUAKE, ON LIFE SUPPORT

A Toyota dealership is seen at a devastated area after the earthquake

and tsunami, in Minamisanriku, Miyagi prefecture, on March 22.

Hundreds of parts suppliers in Toyota City have become victims of

the earthquake and subsequent radiation leak at a power plant

that have disrupted production and distribution in Japan's northeast.


By Automotive News - For Fumihiro Shimizu and his family-owned auto parts plant in this company town, being a second-tier supplier for Japan's top car makers has never been easy.

Even in the boom years, margins were squeezed as Toyota Motor Corp. and others extracted maximum value from suppliers to fight off competition from overseas rivals and keep prices down.


Now, with the magnitude-9.0 earthquake off Japan's eastern coast halting virtually all car assembly in the country since March 11, Shimizu says his company is facing its toughest test yet.


"It's never been this bad," he said. "The areas hit by the tsunami are a mess, but here the auto industry is being strangled. The buildings are standing but inside, we're economically starving to death," he said.


Shimizu Kogyo is one of hundreds of parts suppliers in Toyota City that have become victims of the earthquake and subsequent radiation leak at a power plant that have disrupted production and distribution in Japan's northeast.


With a full-scale recovery expected to be months away, the cost to Japan's $700 billion auto industry will be significant.


And without a clear exit in sight, many say the upshot will be the liquidation of smaller and weaker suppliers that will be unable to meet their payments.


"Many of these companies worked only nine days out of the 23 working days in March," said Yusuke Yamakawa, senior manager at Tokyo Shoko Research's Nagoya branch, near Toyota City.


"Some financially weak subcontractors will inevitably go under starting in April."


Detroit-style decline?


While times are tough and some bankruptcies are expected, few in Japan's Motor City see the risk of a Detroit-style decline.


Detroit's unemployment rate is among the highest in the United States after General Motors Co., Ford Motor Co. and Chrysler shuttered dozens of factories in recent decades as sales fell with increased competition against Asian brands.


Bigger, stronger parts companies in Toyota City could buy up smaller struggling rivals. But without the suppliers at the bottom of the food chain that have long endured low-margin components, Toyota could gradually lose its cozy supply chain that has kept much of its production in Japan.


Although hundreds of kilometers away from the worst-hit regions of the earthquake, tsunami, and radiation, Toyota already appears a changed city.


A shortage of electronics and resin-based components from the region has forced automakers including Toyota and Fuji Heavy Industries Ltd to suspend a majority of their factory lines, resulting in a production loss of at least half-a-million vehicles so far.


The roads are free of the 10-ton trucks that usually carry parts to Toyota's five assembly plants here. Instead, business at pachinko parlours - Japan's most popular form of gambling - is booming. Restaurants are busy with families at lunchtime as factory workers are told to take time off.


Auto parts makers in the city of 420,000 say they have never stopped work for as long as a month. The record so far was two weeks, when Toyota suspended production to work down bloated inventory after the conomic crisis blew up in 2008.


About a fifth of the residents in Toyota City work in the auto manufacturing sector.


Analysts say many small and medium-sized companies still have outstanding loans from the financial crisis, meaning banks will be reluctant to lend further to the companies that need it most.


An official at Toyota City's unemployment office said that over the past few days, his office had fielded 40 to 50 calls from companies asking about government support to keep paying wages in the event they had to fully suspend operations.


Risk management


Already workers are looking for ways to fill in the time they would usually be on the assembly lines.


At one of the pachinko parlours a short drive from Toyota's headquarters, about a dozen rows of slot machines were occupied nearly to capacity with men of working age puffing away at their cigarettes.


"Since the earthquake, I'd say we've seen a 20 to 30 percent rise in traffic," said the store's deputy manager, who asked that he and his store not be identified.


"Because of everything that's going on up north, a business like ours tends to get criticized by people who think it's socially inappropriate to be running an amusement business at a time like this. But with the factories closed, some of those workers need something to pass the time," he said.


While the supply disruption has affected all Japanese automakers and even many overseas, the current debacle was a particularly cruel blow for Toyota.


To spread out its geographic risk, the world's biggest automaker has in recent years begun to establish a third production cluster in Japan in the northeast Tohoku region, which bore the full force of the earthquake and tsunami.


Toyota builds more than two-thirds of its vehicles in Japan in and around its namesake city, and the rest was meant to be spread into the southern Kyushu region and Tohoku.


Toyota Chairman Fujio Cho last month celebrated the opening of subsidiary Central Motor's new, 120,000 units-a-year factory near the badly hit city of Sendai. The plant suffered some damage to its facilities and equipment from the quake.


Toyota is scrambling to get whatever production it can back. So far, it has resumed limited production of the Prius and two other hybrid models at two factories, including the Tsutsumi plant in Toyota City. It is also producing replacement parts and parts for overseas production.


That has helped Okuda Industry, a second-tier supplier, bring its production of engine and transmission parts back up to 70 percent of pre-quake levels in the past two weeks. While his peers in Toyota City say he's lucky, President Kiyohito Okuda said that was far from enough to make money.


"We'll be in the red this month," he said, referring to March. "So if you're operating at 0-20 percent, as I think many suppliers here are, you're past the point of worrying about losing money - it's far, far worse."


The disaster hit just as Toyota's suppliers, like the automaker itself, were recovering from a recall crisis-driven sales drop and the global recession before that.


With a strong yen crippling its domestic operations, Toyota had reduced its daily vehicle production in Japan to around 12,000-13,000 units, or about 70 percent of its peak years. Parts makers say they were just beginning to get by at those reduced levels.


Family businesses to fade


Kosei Aluminium President Sunkichi Kamiya said his company needs to be producing at about four-fifths of capacity to break even - a far cry from around 10-20 percent since the quake. He is assuming a worst-case scenario that a full recovery of car production would take six months - too long for many of the city's debilitated subcontractors further down the supply chain to stay afloat.


"We have an overseas business that's healthy, so we will be able to withstand some pain," Kamiya said.


His company, which makes aluminium wheels and other parts, plans to extend financial support to one of its subcontractors so as not to disrupt production, he said.


Kosei has switched off the man-made waterfall on the company grounds, even though the power source in Toyota City is different from the blackout-affected northeast.


As the pain lasts, Shimizu Kogyo's Shimizu said the end-game for many family-owned suppliers might be to give up and hand over the business to any willing takers.


"Nowadays, you don't find too many families that want to hand down the business to the next generation," said Shimizu, who has no children of his own.


"The one good thing about this business was that it was fairly stable. Now even that's gone. If we reach the end of our rope, I guess we'll just sell the business. I think many people like us have the same thought - how best to end the business."

Tuesday, March 22, 2011

QUAKE HITS JAPANESE AUTO INDUSTRY HARD

By Joseph Bonney, Journal of Commerce - The earthquake and tsunami that killed thousands of people in Japan also disrupted the nation's automobile indfustry and will affect supply chains worldwide, IHS Automotive said.

"Although the human cost is of paramount concern, the ripple effect of the stoppages to supply and production in Japan will be felt in many parts of the world, including the United States, China and Europe as many key parts and technology are exported to global operations from Japan," the report said.

Auto assembly plants and suppliers' factories were damaged or have had to suspend operations because of power shortages. Transportation infrastructure also has been affected, along with communities where automotive workers live.

Several assembly plants in and around the northern Miyagi Prefecture have been shuttered, primarily Toyota, Honda and Nissan facilities, IHS Automotive said.

"Many more auto plants throughout the country are at risk of closure, some owing to temporary rolling blackouts that are being considered in order to conserve power in light of the damage to several Japanese nuclear power plants, and some through disruption to the country's transport infrastructure, affecting everything from parts delivery, personnel mobility and shipping activity at the country's ports."

The report said Toyota will idle all its Japanese plants through Wednesday, halting nearly 45 percent of the company's global production. Nissan reported damage to several plants and suspended all Japanese production through at least Tuesday. Nearly 2,300 vehicles awaiting shipment at the Port of Hitachi were destroyed by the tsunami, Nissan said.

Honda closed its research and development facility north of Tokyo after earthquake damage caused a cafeteria wall to collapse, killing an employee. The company has idled several plants through March 20, including engine, transmission and chassis parts plants.

Suzuki has closed all its Japanese plants until at least Thursday.

Mazda said none of its facilities, located primarily in southern Japan, were affected by the disaster but that it would idle production. Mitsubishi has shuttered plants and said they will remain idle until at least Tuesday as it coordinates shipments with suppliers in the quake-damaged zone.

Subaru said it planned to reopen its plants today after a weekend of shutdown caused by power shortages and damage checks.

JAPAN EARTHQUAKE: CAR PRODUCTION PROBLEMS PERSIST


By Dave Kansas, Wall Street Journal - The Japanese earthquake/tsunami/nuclear disaster is making it tough for Japanese car companies to get production back underway.

Toyota and Honda say that a lack of auto parts has idled plants in Japan. Toyota said its halt will last at least until Saturday, meaning that it will have an output loss of 140,000 vehicles since the quake hit. Honda said production halts through Wednesday will result in an output loss of 27,000 vehicles.

Nissan said it plans to resume auto parts and vehicle production this week.

In New York, Toyota is down about 1%, Honda is off about 3% and Nissan is down almost 6%.

American carmakers aren't faring much better. Ford is off 1.5% and GM is down nearly 2%.

Monday, March 21, 2011

GENERAL MOTORS LAYS OFF WORKERS AT NY PLANT

By Wall Street Journal - General Motors Co. on Monday is halting some production and temporarily laying off workers at a Buffalo, N.Y., engine plant, another sign that Japan's disaster is affecting automakers around the globe.

GM's Tonawanda plant in Buffalo makes four- and five-cylinder engines for the Chevrolet Colorado and GMC Canyon compact pickups, which are assembled at a GM plant in Shreveport, La. GM has shut down the Shreveport plant this week because of a shortage of parts from Japan.

GM spokeswoman Kim Carpenter said Tonawanda has the parts it needs to make the engines, but it's not producing the engines because Shreveport doesn't need them.

She said GM doesn't know when production will resume at either plant.

Carpenter said 59 of the 623 workers at the engine plant will be affected. Workers will get around 75 percent of their pay while they're laid off.

GM hasn't said which parts are affected in Louisiana. Automakers tend to withhold such information for competitive reasons. GM uses a five-speed manual transmission made by Japanese supplier Aisin Seiki Co. in the Canyon and Colorado, but Aisin said last week that it has enough transmissions and parts to continue supplying GM and hasn't shut down any of its plants in North America.

So far, GM is the only U.S.-based automaker to be affected by parts shortages. Ford Motor Co. and Chrysler Group LLC said Monday that they haven't slowed production but are monitoring the situation.

Also Monday, GM slowed production of its Corsa compact car in Europe because of a shortage of parts. GM cancelled two of the three shifts at its Eisenach, Germany, plant and closed another plant in Zaragoza, Spain.

GM said last week it was cutting unnecessary spending companywide as it assesses the impact of production disruptions from the March 11 earthquake and tsunami in Japan.